Turbine Generator Upgrade
Turbine Generator Upgrade
Customer: Confidential Customer
Project Location:
The scope of this project was to add approximately 7.5 MW of power production at a customer’s facility by installing a used 50 psi exhaust, 150psi extraction turbine and generator to 2 existing turbine generators. Harris Group’s scope of work included Class 10 estimate with energy balances, detail design for construction packages, procurement of major equipment, project cost trending, facility-wide power load study and field engineering and commissioning support.